How to Apply for a GEPCO New Connection
Getting a new electricity connection from GEPCO is a straightforward process if you have the required documents. Whether you need a residential, commercial, or industrial connection, this guide will walk you through every step.
Step-by-Step Application Process
- Visit your nearest GEPCO Sub-Division office — Find the GEPCO office responsible for your area. You can call 118 to find your nearest office.
- Submit an application form — Fill out the New Connection Application Form.
- Provide required documents — Submit all necessary documents listed below.
- Pay the demand notice — After inspection, GEPCO will issue a demand notice with fees. Pay at the designated bank.
- Wait for installation — GEPCO will schedule meter installation and connection activation.
- Connection activated — Once the meter is installed, your electricity connection will be live.
Required Documents
For Residential Connection
- Copy of CNIC (National Identity Card)
- Copy of property ownership documents (registry, allotment letter, or rent agreement)
- No Objection Certificate (NOC) from building/housing society (if applicable)
- Passport-size photographs (2 copies)
- Attested copy of the property map/layout plan
For Commercial Connection
- All residential documents listed above
- Business registration certificate or NTN number
- Commercial property proof
- Load requirement details (estimated electricity demand in kW)
Connection Fees
| Connection Type | Load | Approximate Fee |
|---|---|---|
| Residential (Single Phase) | Up to 5 kW | Rs. 5,000 – 8,000 |
| Residential (Three Phase) | 5 – 50 kW | Rs. 15,000 – 40,000 |
| Commercial (Single Phase) | Up to 5 kW | Rs. 8,000 – 12,000 |
| Commercial (Three Phase) | 5 – 100 kW | Rs. 25,000 – 80,000 |
| Industrial | 100+ kW | Rs. 100,000+ |
⚠️ Note: Actual fees depend on load requirement, distance from transformer, and other factors.
Processing Time
- Application to inspection: 3-5 working days
- Demand notice: 7-10 working days after inspection
- Meter installation: 5-15 working days after payment
- Total timeline: Approximately 3-6 weeks
Track Your Application Status
- Calling GEPCO helpline at 118
- Visiting the GEPCO office where you submitted your application
- Checking gepco.com.pk